| PIPELINE MAPS | GEOLOGY | COUNTRIES | USA ENERGY STATISTICS | CHINA STATISTICS | Geographic.org | COUNTRY CODES | AIRPORTS | JOBS |
Deepwater Gulf of Mexico - America's Expanding Frontier
SOURCE: U.S. Department of the Interior, Minerals Management Service, Gulf of Mexico OCS Region






DEVELOPMENT CYCLE

There was considerable lease activity in the late 1980�s (figure 72). (Note that historic deepwater leasing shows no clear relation to average oil or gas prices.)

Figure 72. Deepwater lease activity and oil/natural gas prices (prices from U.S. Energy Information Administration: oil through
September 2003 and natural gas through July 2003). (Click the image to enlarge)
Figure 72. Deepwater lease activity and oil/natural gas prices (prices from U.S. Energy Information Administration: oil through September 2003 and natural gas through July 2003). (Click the image to enlarge)

Acreage at Auger (Garden Banks Block 426) was acquired in 1985 as part of this early activity.

The first Auger well was drilled soon after in 1987.

Even though Auger was leased and drilled early, first production did not begin until 1994, approximately 10 years after the initial lease acquisition.

Acreage at Thunder Horse (Mississippi Canyon Block 778) was acquired in 1988; however, the discovery was not drilled until 1999, and production is not anticipated until 2005. This large gap highlights the considerable lag between leasing and first production.

These lags are not unusual with complex deepwater developments. In contrast, other deepwater projects, such as Typhoon (Green Canyon Block 237) and Constitution (Green Canyon Block 680), have achieved much shorter cycle times.

ChevronTexaco acquired acreage at Typhoon in 1995, drilled the first well in 1998, and began producing the project in 2001. Similarly, acreage at Constitution was acquired in 2001, the first well was drilled that same year, and production is expected to begin in 2006.

These shortened cycle times result from an accessible infrastructure and the use of proven development technologies. Deepwater leasing activity accelerated in the late 1990�s after Congress enacted the Deep Water Royalty Relief Act.

The 3,000 leases that were issued during the record sales from 1996 to 1998 are nearing the end of their primary terms and, therefore, operators are facing key decisions about which leases to relinquish untested. Drilling activities are just beginning to prove the potential of these leases.

There is a significant time period from lease acquisition to first production; however, this interval has decreased from 10 to less than 7 years.

Figures 73a-c demonstrate average lags associated with deepwater operations. These figures use data from only productive deepwater leases.

Figure 73a. Lag from leasing to first well for producing deepwater fields. (Click the image to enlarge)
Figure 73a. Lag from leasing to first well for producing deepwater fields. (Click the image to enlarge)

Figure 73a shows the average number of years it took to drill a well from the time the lease was issued.

Figure 73b shows the average length of time from lease issue to qualification11 of the lease as productive.

Figure 73b. Lag from leasing to qualifying for producing deepwater fields. (Click the image to enlarge)
Figure 73b. Lag from leasing to qualifying for producing deepwater fields. (Click the image to enlarge)

Figure 73c illustrates the lags between leasing, qualification, and first production. There are two lags represented in figures 73a-c.

Figure 73c. Lag from leasing to first production for producing deepwater fields. (Click the image to enlarge)
Figure 73c. Lag from leasing to first production for producing deepwater fields. (Click the image to enlarge)

First, there is a lag between a deepwater discovery and the operator�s request for lease qualification.

Operators sometimes announce discoveries to the public long before qualifying the lease as productive with MMS (and thereby being granted field status).

The second lag depicted in figures 73a-c is the lag between leasing and subsequent operations (drilling, qualifying, and production). Note that, since deepwater leases are in effect for 8 or 10 years, the data are incomplete beyond 1993. The apparent decreasing lags for leases issued after 1993 are explained by the fact that the lease evaluation process has not yet been completed.

The data show an increase from 1976 to 1987 in the number of years before the first well is drilled (figure 73a). This is probably a reflection of two factors.

First, the earliest deepwater leases purchased were of very high interest to the lessees and, therefore, were drilled quickly. Second, increasing lease inventories during the late 1980�s meant that many leases could not be evaluated early in their lease terms (increased deepwater leasing in the mid- to late 1980�s was probably related to the introduction of areawide leasing, the drop in minimum required bid from $150/acre to $25/acre, and the advent of 3-D seismic technology).

During the 1980�s there was a gradual increase in the lag between drilling of the first well and qualifying the lease (figure 73b).

During most of the 1980�s, it took 10-11 years for the average field to come on production. It is important to note, however, that the time between drilling the first well and the beginning of production dropped significantly throughout the 1980�s. That is, operators brought fields online in about 10 years, despite the fact that the first wells were not drilled, on average, until about the fourth year of the lease term by the late 1980�s.

The most recent complete data (many leases issued after 1993 are still in their primary terms) indicate that the time from lease to first production has decreased from over 10 to less than 7 years.

In summary, the latest complete data indicate a three-year average lag between leasing and initial drilling.

There is an additional two-year average lag before the well is qualified, and a total of less than 7 years from lease issuance until production begins.

Another interesting trend is shown in figure 74.

Figure 74. Year in the lease term in which BOE was discovered and percent of leases were tested, for deepwater leases, 1974-1994. (Click the image to enlarge)
Figure 74. Year in the lease term in which BOE was discovered and percent of leases were tested, for deepwater leases, 1974-1994.. (Click the image to enlarge)

For any given lease-sale year, almost 50 percent of tested leases were first drilled within three years of lease acquisition, and 23 percent were drilled in year eight or later.

Twenty-nine percent of the hydrocarbon volumes were discovered during the first three years of their lease terms, but 44 percent of the hydrocarbon volumes were discovered in year eight or later. The data for this analysis include only deepwater leases acquired through 1994, since later leases are still within their primary terms.

As expected, the majority of wells are drilled in the first half of a lease�s primary term, and the majority of hydrocarbons are also found during the same period.

What is surprising is the amount of major discoveries found in the later years of some leases� terms. Certainly, the discoveries of Thunder Horse, North Thunder Horse, and Mad Dog, occurring late in their lease terms, have greatly impacted these volume totals. This demonstrates the difficulty in recognizing the best prospects at the beginning of a lease�s term.


1 An operator may request a �Determination of Well Producibility� from MMS. A successful MMS determination then �qualifies� the lease as producible. Not all qualified leases ultimately begin production.














- Please bookmark this page (add it to your favorites).

Copyright © 1995-2010 ITA all rights reserved.





Cover and Title Page

PREFACE

INTRODUCTION

BACKGROUND

LEASING DRILLING AND DEVELOPMENT RESERVES AND PRODUCTION SUMMARY AND CONCLUSIONS . . . Feedback